I. Material warehouse requirements
1, keep the material warehouse clean, smooth drainage place, away from harmful gas or dust. Remove weeds and debris from the site and keep the steel clean
2, in the warehouse shall not be stacked together with acid, alkali, salt, cement and other corrosive materials to steel. Different types of steel should be stacked separately to prevent confusion and contact corrosion
3, large steel, rail, insult steel plate, large caliber steel pipe, forgings can be stacked in the open air
4, small and medium-sized steel, wire rod, steel bar, medium caliber steel pipe, steel wire and wire rope, etc., can be stored in well-ventilated material shed, but must be on mat mat mat
5. Some small steel, thin steel plate, steel strip, silicon steel sheet, small-caliber or thin-wall steel pipe, all kinds of cold-rolled and cold-drawn steel and high-priced and corrosion-prone metal products must be put into the warehouse
6, pay attention to ventilation in sunny days, pay attention to moistureproof in rainy days, often maintain a suitable storage environment
Two, reasonable stacking, first in first
1. The principle of stacking is to stack according to varieties and specifications under the condition of stable stacking and ensuring safety. Materials of different varieties should be stacked separately to prevent confusion and mutual corrosion
2. It is forbidden to store items corrosive to steel near the stack
3. The bottom of the stack should be high, firm and smooth to prevent the material from damp or deformation
4, the same material according to the storage successively stacked, easy to implement the principle of first in first out
5, the open air pile of steel, there must be wooden mat or stone below, the stack surface is slightly inclined, to facilitate drainage, and pay attention to the material placed straight, to prevent bending deformation
6, stacking height, manual operation shall not exceed 1.2m, mechanical operation shall not exceed 1.5m, stacking width shall not exceed 2.5m
7. There should be a certain passage between the stack and the stack. The inspection passage is generally O. 5m, and the access passage depends on the size of the material and the transportation machinery, generally 1.5 ~ 2
8, stack bottom pad high, if the warehouse is chaoyang cement floor, pad high O. 1M can be; If it is mud, it must be O. 2 ~ 0.5m high. If it is an open site, the cement floor pad height is O·3 ~ O·5m, and the sand and mud surface pad height is 0.5 ~ O
9, the open air pile Angle and channel steel should be bent, that is, the mouth down, I steel should be put up, I groove surface of steel can not be up, so as not to rust water.
Keep the warehouse clean and strengthen the maintenance of materials
1, the material before storage should pay attention to prevent rain or mixed with impurities, the material has been wet or dirty according to its properties using different methods to wipe, such as high hardness of steel wire brush, low hardness of cloth, cotton and other things
2, the material should be checked regularly after storage, if there is rust, should remove the rust layer
3, general steel surface after cleaning, do not need to be coated with oil, but for high quality steel, alloy thin steel plate, thin wall pipe, alloy steel pipe, rust removal of its internal and external surface should be coated with anti-rust oil before storage
4. The steel with serious rust should not be kept for a long time after rust removal and should be used as soon as possible.
Please give us a message